Fermi: the turbines are here, the tenant isn't signed

Position

San Jacinto Capital rates Fermi (FRMI) Hold. We hold no position in Fermi or any other company named in this piece. This piece is impersonal general commentary, not individualized advice.

Fermi, Amarillo, Texas, November 2026

Fermi went up 14% on Thursday and 27% on Friday. In two days the market added roughly half a billion dollars to a company that has never booked a dollar of revenue.

The reason was a $200 million prepayment from an investment grade hyperscaler for 600 megawatts of power at Fermi's campus outside Amarillo. The Financial Times reported Friday that the customer is Amazon. Fermi has not named it. Fermi also has not signed a lease, and it has announced a tenant twice before and lost both.

Rating: Hold

Street average price target: $16.63 (8 analysts polled by S&P Global, as of Oct. 16, 2026; low $6, high $35). Price at publication: $2.61, the November 13, 2026 close.

Is the project real? Yes, and further along than the stock price suggests. Fermi has spent nearly $1.7 billion. Its gas turbine air permit is approved, all six of its GE turbines and five of six Siemens turbines are on site, and it has about 2 gigawatts of generation secured. First power is targeted for mid 2027.

Is the customer real? The money is. The hyperscaler paid $200 million up front and signed a $15 million construction agreement, which is a good deal more than a letter of intent. But the definitive long term lease is not signed, and its value and term are not disclosed. Fermi's two previous tenants both walked. A prospective tenant canceled a $150 million funding agreement in December 2025. TensorWave signed a $6.5 billion, 222 megawatt lease in August, and on Thursday Fermi announced it had been terminated.

Can it pay for what it is building? Not on its own yet. Fermi ended September with $315.5 million in cash and restricted cash against $958.4 million of debt, up from $109.8 million at the start of the year. It lost $141.6 million in the third quarter and spent $133.4 million on construction. The prepayment buys time. It takes rent from a signed lease to service the debt.

Is it cheap? Maybe. With about 646 million shares outstanding, the market value at $2.61 is roughly $1.7 billion, about what Fermi has already put into the ground. The Street's average target is more than six times the current price, but those targets are a month old and predate the TensorWave termination.

Why not a Buy? Because the company is one signature away from a very different stock, and it has been one signature away before. We would rather pay more after the lease is signed than less before it.

What changes the rating? A signed definitive lease with the hyperscaler, with value and term disclosed. The rest of the conditions are at the end of this piece.

What the company is

Fermi is building a private power and data center campus called Project Matador on about 5,000 acres of Texas Tech University System land in Carson County. The site is roughly 15 miles northeast of Amarillo, next to the Pantex nuclear weapons plant. Texas Tech signed a 99 year ground lease with Fermi in 2025.

The plan is to generate power on site and sell it, along with the buildings, to data center tenants behind the meter. Gas comes first. Fermi calls it the country's largest combined cycle gas project, with about 2.2 gigawatts of capacity today and permits sought for 5 gigawatts more. Nuclear comes later. Fermi has applied to the Nuclear Regulatory Commission for four Westinghouse AP1000 reactors, about 4 gigawatts in all. Solar, batteries and up to 200 megawatts of grid power from Xcel fill in the rest. The company says the site could eventually reach 11 gigawatts or more.

Fermi was cofounded by Rick Perry, the former Texas governor and Energy Secretary. It listed on the Nasdaq and the London Stock Exchange in October 2025.

The quarter

Fermi has no revenue. The third quarter net loss was $141.6 million, or $0.22 a share, compared with $346.8 million a year earlier. General and administrative costs were $142.2 million. Of that, $65.8 million was stock compensation and another $21.5 million was fees paid in stock. Construction spending was $133.4 million for the quarter and $759.5 million for the first nine months.

On financing, Fermi repaid its $144.3 million Macquarie term loan and added $463 million in net borrowings through convertible notes and equipment loans. In October it paid $25 million in fees to amend its turbine loan with MUFG. The amendment removed a covenant that required a 400 megawatt lease by November 10. Fermi would not have met it.

The bull case

The hardware is on the ground. Most of what gets announced in AI power is a press release and a parcel of land. Fermi has an approved air permit, turbines on site, and a mid 2027 target for first power, with up to 925 megawatts available that year.

It sits outside ERCOT. The Panhandle site is on the Southwest Power Pool, not the Texas grid. In August Governor Abbott ordered an audit of data centers seeking ERCOT connections, and data centers on the Texas grid have become a political target in Austin. Fermi is largely out of that fight.

A hyperscaler put cash down. If the customer is Amazon, Fermi has the most creditworthy tenant a project like this can get. Nobody prepays $200 million casually.

It trades near what it has spent. At about $1.7 billion, the market is paying roughly the cost of what is already built. The permits, the land lease and the nuclear option come nearly free.

The bear case

Two tenants have already walked. Until a definitive lease is signed, Fermi has a prepayment and no contracted revenue.

Debt is up about ninefold. It reached $958 million this year at a company with no revenue. More convertibles or new equity would dilute current shareholders.

Nuclear keeps slipping. Fermi now expects its reactors one a year from 2034 through 2037. That is a year later than its previous filing and two years later than the original plan for 2032. Nothing nuclear helps this stock before the middle of the next decade.

Governance has been rough. Cofounder and chief executive Toby Neugebauer was removed in April and fired for cause, and he has sued. At the October 30 annual meeting, directors Rick Perry and Jeffrey Stein did not receive the votes needed for reelection and remain as holdovers. Lee McIntire is now chief executive.

Deadlines are close. Under its agreement with Texas Tech, Fermi must post a $9 million escrow by December 31, 2026, before vertical construction can proceed on the university's terms.

What it means for the Panhandle

The campus is in Carson County, inside Panhandle ISD, and Amarillo is the city it leans on. Carson County approved a phased tax abatement in 2025, with payments in lieu of taxes set per megawatt and per square foot. Fermi has said the project could support about 5,475 permanent jobs at full buildout, a figure from its own filing. It also has a water contract with the City of Amarillo that it says is worth more than $7 million a year.

The objections are the ones every large Panhandle project hears. Residents and groups including the Sierra Club have raised questions about groundwater and about taxes. The region runs on the Ogallala Aquifer, and water is the risk most likely to slow a campus this size.

For Amarillo, the upside is construction work now and, if the tenants sign, a new kind of employer in a city built on cattle, wheat and Pantex.

What we would want to see

What would make this a strong buy:

  • A signed definitive lease with the hyperscaler, with value and term disclosed
  • First power delivered on the mid 2027 target
  • The Texas Tech escrow posted and notice to proceed received by December 31
  • A second tenant for the remaining capacity
  • Financing that carries the project to first power without heavy dilution

Fermi has turbines on site, an approved permit and a hyperscaler's cash. It does not have a lease. If one gets signed, this rating moves. Until then we are watching.

This piece is general commentary on public information and is not individualized advice or an offer to buy or sell any security. The rating is San Jacinto Capital's opinion. We hold no position in Fermi (FRMI) or any other company named in this piece. Do your own research.

Sources

  1. Fermi third quarter 2026 results.
  2. U.S. Securities and Exchange Commission.
  3. S&P Global via Stock Analysis.
  4. Financial Times.
  5. Texas Commission on Environmental Quality.
  6. U.S. Nuclear Regulatory Commission.
  7. Amarillo Ledger.
  8. Investing.com.